Renovation Update, Part 21

Hello everyone,

Lots of flooring this week! The tile crew continues to do a great job, and you can clearly see the outline of the new pew arrangement. The new location for the baptismal font features a special design in the floor, and it looks incredible. The church flooring has been a huge project, but the completion is now in sight!

A carpeting crew also worked on the lobby, cry room, narthex, and stairways. Having the same flooring in these areas really adds some continuity to the entryway, and looks great!

Work continues on other parts of the project as well. Up in the choir loft the new music library received drywall. On the carpentry front, trim work began on the confessional/usher closet.

There’s lots getting done and lots left to go, but we’re getting there!

Peace,

Fr. Brandon